Underground / HDD· sample listing
HDD crews, caliche and cobble, 4-inch conduit
Panhandle Underground · Northwest OK and southern KS (OK, KS) · posted 3d ago
$5.85 / ft
$185 per diem
$185 × 6 = $1,110 / wk
Net 15
Paid on days worked
- Prime contractor
- Sunbelt Fiber Group
- Start date
- Targeted start Oct 12
- Work status
- Awarded, waiting on NTP
- Duration
- 32 weeks · 6 days a week
- Headcount
- 9 crew positions
- Hiring
- Full crews
- States
- OK, KS
What this job requires of you, as posted
- Paid as
- 1099
- Truck and gear
- You bring your own truck and gear
- Travel
- Road crews welcome
- Per diem
- Paid on days worked
Before you dig
- KS — Kansas 811 needs 2 working days notice, tolerance 24" each side.Ticket good 20 calendar days from the start date you put on the ticket.Two full working days. Max 20 calendar days.24 inches from the facility's outside dimensions. Larger water mains may elect up to 60 inches.The notice period and the tolerance zone live in different sections of the statute — §66-1804 sets the wait, §66-1802 defines the zone. Reading only the first gets you a valid ticket and a wrong hand-dig width.K.S.A. §§66-1802 (tolerance), 66-1804 (notice and ticket life)
- OK — OKIE811 needs 48 hours notice, tolerance 24" each side.Ticket good 14 calendar days from the start date you put on the ticket.48 hours excluding the date of notification, weekends and holidays. Clock starts the day after. No maximum in the current text.24 inches each side.63 O.S. 142.1 et seq., §§142.6, 142.7
Check the ticket yourself before the first bore. This is a starting point, not legal advice, and the clock does not always start when you call.
Scope
Mainline conduit along county section roads. Caliche with cobble in the western half. Prime handles permits and traffic control. Restoration by others.
Contact
Dee Whitlock · (555) 402-7781