New Mexico: 2 working days before you dig.
New Mexico 811 · NMSA 1978 §§62-14-2, 62-14-3
Read off the statute on . If it has moved since, tell us and we will re-read it.
A waiting period is not always permission. Some states also require that every operator has answered before you break ground, and some require you to mark your own dig path first. Where we have read that requirement, it is in the notes on this page. Where this page is silent, we have not checked it yet — silence here is not the same as absence. We are working through the rest and dating each one as it lands.
Notice before you break ground
2 working days
Two working days — the statute defines 'advance notice' as exactly that and then uses the phrase throughout, so there is no separate number to look up.
Tolerance zone
18" each side
Eighteen inches between the facility itself and the cutting edge or point of any mechanical equipment, until the line is first exposed. Measured from the line, not from the paint.
Ticket good for
10 working days from the day you call
Worth knowing in New Mexico
New Mexico never says a ticket expires. It says you must request reaffirmation of line location every ten working days after the initial request, which comes to the same thing on site. The definitions section backs the figure up from the other end: a legal mark is one 'designed to last at least ten working days if not disturbed'. Positive response is available and the statute expects you to use it before you commute to the site.
Common questions about digging in New Mexico
- How much notice do you have to give before digging in New Mexico?
- 2 working days before you break ground, through New Mexico 811. Two working days — the statute defines 'advance notice' as exactly that and then uses the phrase throughout, so there is no separate number to look up.
- How long is an 811 ticket good for in New Mexico?
- 10 working days from the day you call.
- What is the tolerance zone in New Mexico?
- 18" each side. Eighteen inches between the facility itself and the cutting edge or point of any mechanical equipment, until the line is first exposed. Measured from the line, not from the paint.
Check it yourself
Every figure here was read off NMSA 1978 §§62-14-2, 62-14-3, not off a summary — summaries of these get the unit wrong, and the unit is usually a weekend. Read the source.