Nevada: 2 working days before you dig.
USA North 811 · NRS ch. 455, §§455.082, .105, .110, .137; NAC 455.165
Read off the statute on . If it has moved since, tell us and we will re-read it.
A waiting period is not always permission. Some states also require that every operator has answered before you break ground, and some require you to mark your own dig path first. Where we have read that requirement, it is in the notes on this page. Where this page is silent, we have not checked it yet — silence here is not the same as absence. We are working through the rest and dating each one as it lands.
Notice before you break ground
2 working days
Two working days, counted 7 a.m. to 5 p.m. Clock starts the day after. Max 28 calendar days.
Tolerance zone
24" each side
Ticket good for
28 calendar days from when the centre receives your notice
Worth knowing in Nevada
Two extensions maximum, so roughly 84 days is the ceiling on one ticket.
Common questions about digging in Nevada
- How much notice do you have to give before digging in Nevada?
- 2 working days before you break ground, through USA North 811. Two working days, counted 7 a.m. to 5 p.m. Clock starts the day after. Max 28 calendar days.
- How long is an 811 ticket good for in Nevada?
- 28 calendar days from when the centre receives your notice.
- What is the tolerance zone in Nevada?
- 24" each side.
Check it yourself
Every figure here was read off NRS ch. 455, §§455.082, .105, .110, .137; NAC 455.165, not off a summary — summaries of these get the unit wrong, and the unit is usually a weekend. Read the source.